A bi-objective optimization for finance-based and resource-constrained robust project scheduling

被引:7
|
作者
Liu, Wanlin [1 ,2 ]
Zhang, Jingwen [1 ,3 ]
Liu, Cuifang [1 ]
Qu, Chunli [2 ]
机构
[1] Northwestern Polytech Univ, Sch Management, Xian 710072, Peoples R China
[2] Sichuan Agr Univ, Sch Architecture & Urban Rural Planning, Chengdu 611830, Peoples R China
[3] Northwestern Polytech Univ, Sch Management, 127 West Youyi Rd, Xian 710072, Shaanxi Provinc, Peoples R China
基金
中国国家自然科学基金;
关键词
Finance-based project; Robust project scheduling; Bi-objective optimization; NET PRESENT VALUE; GENETIC ALGORITHM; CONSTRUCTION PROJECTS; HEURISTIC PROCEDURES; CASH FLOWS; NSGA-II; MANAGEMENT; MAXIMIZE; NETWORK; MODEL;
D O I
10.1016/j.eswa.2023.120623
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
Numerous finance-based projects encounter disturbances from a variety of uncertain factors during their execution, under which both the original baseline schedule and financing alternative become infeasible. How-ever, many previous studies on the finance-based project scheduling problem (FBSP) neglected a potential feature of stochastic activity durations. In this paper, we address the issue of generating a robust project schedule that not only satisfies financing credit and renewable resource limits, but also tackles disruptions due to activity uncertainty. A bi-objective model for finance-based and resource-constrained robust project scheduling problem (FBRCRPSP) is constructed, where the trade-off between profit and robustness is considered. Based on the transformed integer programming model, an exact procedure of & epsilon;-constraints is proposed to obtain Pareto-optimal solutions for small-sized instances. For large-scale projects, a non-dominated sorting genetic algorithm with local search (NSGA-II-LS) that deeply explores the neighboring solution space is developed, in which a generic procedure with two new recursion policies is proposed to determine the robustness of schedules. Benchmarking is conducted to evaluate the efficiency of the algorithms via some performance criteria. The re-sults show that all developed approaches have good performance in small-sized instances, and the NSGA-II-LS outperforms the non-dominated sorting genetic algorithm without local search (NSGA-II) in terms of the spread, convergence, and diversity of Pareto-optimal solutions significantly. In addition, some managerial in-sights are summarized to enlighten project managers.
引用
收藏
页数:18
相关论文
共 50 条
  • [1] Bi-objective Optimization for Resource-constrained Robust Construction Project Scheduling
    Wanlin Liu
    Li Ge
    Chunli Qu
    Shun Yang
    KSCE Journal of Civil Engineering, 2024, 28 : 15 - 28
  • [2] Bi-objective Optimization for Resource-constrained Robust Construction Project Scheduling
    Liu, Wanlin
    Ge, Li
    Qu, Chunli
    Yang, Shun
    KSCE JOURNAL OF CIVIL ENGINEERING, 2024, 28 (01) : 15 - 28
  • [3] A bi-objective model for robust resource-constrained project scheduling
    Al-Fawzan, MA
    Haouari, M
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2005, 96 (02) : 175 - 187
  • [4] Heuristic Methods for Finance-Based and Resource-Constrained Project Scheduling Problem
    Liu, Wanlin
    Zhang, Jingwen
    Li, Wanjun
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (11)
  • [5] Hybrid genetic algorithm for bi-objective resource-constrained project scheduling
    Fikri Kucuksayacigil
    Gündüz Ulusoy
    Frontiers of Engineering Management, 2020, 7 : 426 - 446
  • [6] Hybrid genetic algorithm for bi-objective resource-constrained project scheduling
    Kucuksayacigil, Fikri
    Ulusoy, Gunduz
    FRONTIERS OF ENGINEERING MANAGEMENT, 2020, 7 (03) : 426 - 446
  • [7] Bi-objective resource-constrained project scheduling with robustness and makespan criteria
    Abbasi, Babak
    Shadrokh, Shahram
    Arkat, Jamal
    APPLIED MATHEMATICS AND COMPUTATION, 2006, 180 (01) : 146 - 152
  • [8] A bi-objective Model for Robust Resource-constrained Project Scheduling Problem with Random Activity Durations
    Zhang, Jingwen
    Qiao, Chuanzhuo
    2015 IEEE 12th International Conference on Networking, Sensing and Control (ICNSC), 2015, : 28 - 32
  • [9] Performance of Priority Rules for Finance-Based and Resource-Constrained Project Scheduling Heuristics
    Liu, Wanlin
    Zhang, Jingwen
    Qu, Chunli
    Zhang, Haotian
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2024, 150 (06)
  • [10] Bi-objective resource-constrained project scheduling problem with time-dependent resource costs
    Alcaraz, Javier
    Anton-Sanchez, Laura
    Saldanha-da-Gama, Francisco
    JOURNAL OF MANUFACTURING SYSTEMS, 2022, 63 : 506 - 523