Investigation of cracking mechanism of the first tunnel lining during double-arch tunnel construction

被引:7
|
作者
Sui, Yi [1 ]
Cheng, Xiaohui [2 ]
Zhao, Zuozhou [2 ]
Ma, Weibin [1 ]
机构
[1] China Acad Railway Sci Corp Ltd, Railway Engn Res Inst, Beijing 100081, Peoples R China
[2] Tsinghua Univ, Sch Civil Engn, Beijing 100084, Peoples R China
基金
中国国家自然科学基金;
关键词
Double-arch tunnel; Cracking mechanism; Distributed optical-fibre sensing; Inversion analysis; Total strain rotating crack model; Load-structure method; OPTICAL-FIBER; MODEL;
D O I
10.1016/j.undsp.2023.05.011
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
To solve the engineering problem of the first tunnel lining cracking caused by the second tunnel construction of double-arch highway tunnels, a research method combining distributed optical-fibre monitoring, inversion analysis and numerical simulation that can reflect lining cracking was presented. Optical fibres were laid on opposite sides of the steel arches inside the first tunnel lining. Embedded optical-fibre monitoring was conducted continuously during the second tunnel driving. Based on the fibre-optic strain profile, the lining cracking was deduced and warned in time. The mechanical behaviour of the steel arch was investigated by the inversion analysis, which took into consideration the integrated impact of axial force and flexural moment. A two-dimensional (2D) load-structure method-based numerical model was established, considering the influence of different load distributions in each construction condition. The total strain rotating crack constitutive model was applied to reflect the cracking behaviour of concrete lining in the simulation, and the model was calibrated and verified in the laboratory. Comparative analysis between the simulated strain distribution and the distributed optical-fibre monitoring results was carried out. The deformation mode and crack distribution of the lining were analysed. The cracking mechanism was explained. Specifically, the second tunnel construction led to the loading at the top of the middle partition wall and the release of rock pressure in the first tunnel. Under these load changes, the secondary lining of the first tunnel cracked on the inner side of the top of the middle partition wall owing to tension, and compression-bending failure occurred near the right arch foot. Finally, the influence of the parameters on the lining force was analysed, and a construction optimisation scheme was proposed.
引用
收藏
页码:1 / 17
页数:17
相关论文
共 50 条
  • [1] CONSTRUCTION TECHNOLOGY OF PERMEABLE RIB DOUBLE-ARCH TUNNEL
    Song, Ruijun
    Yu, Fei
    Chen, Shanxiong
    Chen, Xiuhe
    Wang, Fei
    PROCEEDINGS OF THE 4TH INTERNATIONAL CONFERENCE ON MECHATRONICS, MATERIALS, CHEMISTRY AND COMPUTER ENGINEERING 2015 (ICMMCCE 2015), 2015, 39 : 2938 - 2944
  • [2] Mechanical Characteristics of an Open-Buried Double-Arch Tunnel during Construction
    Lin, Yu-Liang
    Guo, Ya-Lin
    Yang, Guo-Lin
    Zhang, Pei-Ran
    APPLIED SCIENCES-BASEL, 2023, 13 (06):
  • [3] Deformation mechanism of a shallow double-arch tunnel in a sloping rock mass
    Huang Runqiu
    Xiao Huabo
    BULLETIN OF ENGINEERING GEOLOGY AND THE ENVIRONMENT, 2010, 69 (01) : 89 - 97
  • [4] Deformation mechanism of a shallow double-arch tunnel in a sloping rock mass
    Huang Runqiu
    Xiao Huabo
    Bulletin of Engineering Geology and the Environment, 2010, 69 : 89 - 97
  • [5] Displacement and Deformation of the First Tunnel Lining During the Second Tunnel Construction
    Wu, Lin
    Zhang, Xiedong
    Zhang, Zhihua
    Luo, Luqing
    Sun, Weichen
    CIVIL ENGINEERING JOURNAL-TEHRAN, 2019, 5 (02): : 332 - 339
  • [6] Study of the influence of double-arch tunnel construction on ground water seepage field
    Zhuo, Yue
    Wang, Mengshu
    Zhou, Dongyong
    Tumu Gongcheng Xuebao/China Civil Engineering Journal, 2010, 43 (05): : 104 - 110
  • [7] In-situ tests on lining system of double-arch tunnel with shallow large section and span
    Zhou, Ding-Heng
    Cao, Li-Qiao
    Wang, Xiao-Xing
    Fang, Shi-Tao
    Yantu Gongcheng Xuebao/Chinese Journal of Geotechnical Engineering, 2010, 32 (10): : 1573 - 1581
  • [8] Mechanism of inverted arch floor heaving and secondary lining cracking of the multi-arch tunnel
    Bai, Guoquan
    Modern Tunnelling Technology, 2014, 51 : 143 - 150
  • [9] 3D numerical simulation of a large span double-arch tunnel construction
    Xia, C. C.
    Liu, H. J.
    Zhu, H. H.
    COMPUTATIONAL METHODS, PTS 1 AND 2, 2006, : 1853 - +
  • [10] Time-Varying Response Analysis of Surrounding Rock Construction Mechanics of a Double-Arch Tunnel without a Middle Pilot Tunnel and Suggestions for Tunnel Construction
    Xie, Caijin
    Tao, Tiejun
    Rao, Junying
    Lithosphere, 2022, 2022 (SpecialIssue10)