Study on the critical factors of the successful construction using the incremental launching method (ILM) for a steel cable-stayed bridge

被引:0
|
作者
Su, Ming-Chao [1 ]
Tserng, Hui-Ping [1 ]
Chen, Gong [1 ]
机构
[1] Natl Taiwan Univ, Dept Civil Engn, Taipei, Taiwan
关键词
Steel girder cable-stayed bridge; incremental launching method; scaffolding method;
D O I
10.1080/02533839.2025.2456482
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The construction of steel-structure bridges is faster and less damaging to the environment than that of concrete bridges. However, the traditional scaffolding method often used to construct steel bridges fail to fully exploit these advantages. The incremental launching method (ILM) minimizes traffic disruption and working space during construction; therefore, this method is ideal for inaccessible sites or where construction interference must be minimized. Despite its benefits, ILM is primarily used for constructing concrete bridges; it has rarely been applied for constructing steel-structure bridges. This article explores the advantages and applicability of the ILM for constructing steel-structure cable-stayed bridges by considering the new Dazhu Bridge in Taoyuan, Taiwan, as a case study. This bridge spans a 110-m highway, and its design requirements prohibit the creation of piers on the highway or the disruption of highway traffic. We compared the performance of the ILM and scaffolding method for single-span cable-stayed bridges with a focus on structural models, usage specifications, and construction methods. The incremental launching of steel structures can considerably reduce traffic interference and construction time while improving construction quality and safety. This method combines techniques for concrete bridge superstructure construction, such as the precast segment method, ILM, and ASM.
引用
收藏
页码:146 / 157
页数:12
相关论文
共 50 条
  • [1] El Carrizo bridge - Cantilever construction of a cable-stayed bridge launching girders deck using
    Trotin, Nicolas
    Ladret, Patrick
    del Olmo, Sergio
    HORMIGON Y ACERO, 2015, 66 (275): : 69 - 83
  • [2] Study on the seismic retrofit of a steel cable-stayed bridge
    Otsuka, H
    Yamahira, K
    Kusuda, H
    EARTHQUAKE RESISTANT ENGINEERING STRUCTURES III, 2001, 9 : 641 - 650
  • [3] STUDY ON OPTIMAL CONSTRUCTION METHOD FOR LOWER BEAM OF CABLE-STAYED BRIDGE TOWERS
    Liu, Yun
    Yan, Donghuang
    Tu, Guangya
    INTERNATIONAL SYMPOSIUM ON LIFE-CYCLE PERFORMANCE OF BRIDGES AND STRUCTURES, 2010, : 1032 - 1035
  • [4] Accelerated construction and geometry control for cable-stayed bridge using novel cable crane method
    Yu, Xiangmin
    Zhu, Yichen
    Chen, Dewei
    Liu, Jin
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-CIVIL ENGINEERING, 2024,
  • [5] A Stability Study of the Longest Steel Truss Deck Cable-stayed Bridge during Construction
    Xiang-min Yu
    De-wei Chen
    Zhi-zhou Bai
    KSCE Journal of Civil Engineering, 2019, 23 : 1717 - 1724
  • [6] A Stability Study of the Longest Steel Truss Deck Cable-stayed Bridge during Construction
    Yu, Xiang-min
    Chen, De-wei
    Bai, Zhi-zhou
    KSCE JOURNAL OF CIVIL ENGINEERING, 2019, 23 (04) : 1717 - 1724
  • [7] Prediction of Parameters Error in Method of Construction Control in Cable-Stayed Bridge
    Chen, Changsong
    Yan, Donghuang
    Dong, Daofu
    ADVANCES IN STRUCTURES, PTS 1-5, 2011, 163-167 : 2385 - 2389
  • [8] Incremental Launching Construction Method for Steel Truss Suspension Bridge
    Xu, Kaiming
    ADVANCED RESEARCH ON INDUSTRY, INFORMATION SYSTEMS AND MATERIAL ENGINEERING, PTS 1-7, 2011, 204-210 : 842 - 845
  • [9] Nondestructive testing method and technique for cable-stayed bridge steel cables
    Wu, XJ
    Kang, YH
    Chen, HG
    ADVANCES IN NONDESTRUCTIVE EVALUATION, PT 1-3, 2004, 270-273 : 1493 - 1499
  • [10] Analysis on Vertical Swivel Construction of Cable-Stayed Bridge with Steel Arch Pylon
    Li, Qionghui
    Wang, Xiangyang
    Han, Lili
    APPLIED MECHANICS AND MATERIALS II, PTS 1 AND 2, 2014, 477-478 : 635 - 639