Preliminary decontamination and decommissioning plan for the Tokamak Fusion Test Reactor

被引:0
|
作者
Walton, G.R. [1 ]
Commander, J.C. [1 ]
机构
[1] Princeton Plasma Physics Lab, Princeton, NJ, United States
来源
Fusion Technology | 1992年 / 21卷 / 3 pt 2B期
关键词
Deuterium - Nuclear Reactors; Fusion--Decommissioning; -; Tritium;
D O I
10.13182/fst92-a30025
中图分类号
学科分类号
摘要
The Tokamak Fusion Test Reactor (TFTR) Preliminary Decontamination and Decommissioning (D&D) Plan was developed to provide a framework for estimating the costs and schedule for implementing a final D&D Plan. This work will be used in evaluating the future use of the TFTR Test Cell. D&D planning and estimates were generated for two cases of plasma operations for TFTR. The first scenario is for continued operation in deuterium-deuterium (D-D) plasmas and subsequent decommissioning. This scenario would require D&D to a TFTR which is slightly activated and contaminated but still with a capability for 'hands-on' D&D work. The second scenario calls for deuterium-tritium (D-T) plasma operations. In this scenario TFTR becomes highly activated and contaminated with tritium. This operational scenario will result in a TFTR which will require D&D involving remote handling. The end result in either scenario would provide a Test Cell which is available for future use. This paper will discuss the D&D objectives, management, safety and technical plans, and critical assumptions made in order to develop cost and schedule estimates.
引用
收藏
页码:2062 / 2066
相关论文
共 50 条
  • [1] PRELIMINARY DECONTAMINATION AND DECOMMISSIONING PLAN FOR THE TOKAMAK FUSION TEST REACTOR
    WALTON, GR
    COMMANDER, JC
    FUSION TECHNOLOGY, 1992, 21 (03): : 2062 - 2066
  • [2] Decontamination and decommissioning of the Tokamak Fusion Test Reactor
    Perry, E
    Chrzanowski, J
    Rule, K
    Strykowsky, R
    Viola, M
    Williams, M
    18TH IEEE/NPSS SYMPOSIUM ON FUSION ENGINEERING, 1999, : 97 - 100
  • [3] Decommissioning of the Tokamak Fusion Test Reactor
    Perry, E
    Chrzanowski, J
    Gentile, C
    Parsells, R
    Rule, K
    Strykowsky, R
    Viola, M
    20TH IEEE/NPSS SYMPOSIUM ON FUSION ENGINEERING, PROCEEDINGS, 2003, : 256 - 259
  • [4] Industrial hygiene concerns during the decontamination and decommissioning of the Tokamak Fusion Test Reactor
    Lumia, ME
    Gentile, CA
    19TH IEEE/NPSS SYMPOSIUM ON FUSION ENGINEERING, PROCEEDINGS, 2002, : 111 - 113
  • [5] Technology issues for decommissioning the tokamak fusion test reactor
    Spampinato, P.T.
    Commander, J.C.
    Walton, G.R.
    Fusion Technology, 1994, 26 (3 pt 2): : 1030 - 1033
  • [6] TECHNOLOGY ISSUES FOR DECOMMISSIONING THE TOKAMAK FUSION TEST REACTOR
    SPAMPINATO, PT
    COMMANDER, JC
    WALTON, GR
    FUSION TECHNOLOGY, 1994, 26 (03): : 1030 - 1033
  • [7] TOKAMAK FUSION REACTOR RESEARCH AND DEVELOPMENT PLAN
    DEAN, SO
    TRANSACTIONS OF THE AMERICAN NUCLEAR SOCIETY, 1975, 21 (JUN): : 14 - 14
  • [8] CONSTRUCTION OF THE TOKAMAK FUSION TEST REACTOR
    FRENCH, JW
    FEDOR, BJ
    SHAW, LE
    SABADO, MM
    NUCLEAR TECHNOLOGY-FUSION, 1983, 4 (02): : 326 - 335
  • [9] TOKAMAK FUSION TEST REACTOR EXPERIMENT
    FURTH, HP
    BULLETIN OF THE AMERICAN PHYSICAL SOCIETY, 1976, 21 (01): : 94 - 94
  • [10] TOMOGRAPHY ON TOKAMAK FUSION TEST REACTOR
    NAGAYAMA, Y
    REVIEW OF SCIENTIFIC INSTRUMENTS, 1994, 65 (11): : 3415 - 3422