Analysis of the deformation induced by the advance pre-reinforcement construction of a large cross-section tunnel in water-rich sandy rock

被引:0
|
作者
Li, Hui [1 ]
Yu, Shaohui [1 ]
Yang, Chaoshuai [1 ]
Bai, Zhongkun [1 ]
Zhu, Dehua [2 ]
机构
[1] Technology Center of China Railway Tunnel Group, Luoyang 471009, China
[2] College of Planning and Architectural Engineering, Henan University of Science and Technology, Luoyang 471003, China
关键词
Railroad tunnels - Concrete construction - Extrusion - Grouting - Finite element method - Deformation - Mortar;
D O I
暂无
中图分类号
学科分类号
摘要
As for the engineering characteristics of sandy rock, advance pre-reinforcement with horizontal jet grouting was applied in the large cross section of the Taoshuping Tunnel on the Lanzhou-Chongqing Railway. This paper presents a detailed analysis of the extrusion deformation, pre-displacement, crown settlement, and convergence that was carried out by finite element numerical simulation and theoretical calculations combined with field monitoring data. The analysis shows: 1) the initial maximum displacement rate is in direct proportion to the final accumulative displacements; 2) Crown settlement and convergence displacement present obvious spatial effects; and 3) Crown settlement and convergence displacement have certain relevance.
引用
收藏
页码:128 / 137
相关论文
共 22 条
  • [1] Similarity model test study of pre-reinforcement measures of shallow tunnel with large cross-section
    Li Hua-yun
    Zhang Zhi-qiang
    Wang Zhi-jie
    Ling Yun-peng
    Zhang Hao
    ROCK AND SOIL MECHANICS, 2012, 33 : 133 - 138
  • [3] Study on the Grouting Pre-Reinforcement Mechanism and Effect Evaluation in Water-rich Loess Tunnel
    Xue, Xiaohui
    Zhang, Jun
    Su, Zhongming
    PROCEEDINGS OF THE 5TH INTERNATIONAL CONFERENCE ON ADVANCED DESIGN AND MANUFACTURING ENGINEERING, 2015, 39 : 1084 - 1088
  • [4] The Analysis Method of Rock Mass Deformation of Large Cross-section Tunnel
    Chen, Chun-hui
    Wu, Li
    Peng, Ya-xiong
    GEOTECHNICAL AND GEOLOGICAL ENGINEERING, 2016, 34 (02) : 739 - 743
  • [5] An extended discontinuous deformation analysis for simulation of grouting reinforcement in a water-rich fractured rock tunnel
    Gao, Jingyao
    Peng, Siyu
    Chen, Guangqi
    Fan, Hongyun
    JOURNAL OF ROCK MECHANICS AND GEOTECHNICAL ENGINEERING, 2025, 17 (01) : 168 - 186
  • [6] Risk analysis and control study of super-shallow tunnel with large cross-section under water-rich channel
    Shi Yu-feng
    Yang Jun-sheng
    Shao Hua-ping
    Long Yun
    Yang Feng
    ROCK AND SOIL MECHANICS, 2012, 33 : 229 - 234
  • [7] Optimization design of pre-reinforcement scheme for large cross section shallow buried tunnel in Xi'an Metro
    Gao Xiao-mei
    Dai Jian-bo
    2017 2ND INTERNATIONAL SEMINAR ON ADVANCES IN MATERIALS SCIENCE AND ENGINEERING, 2017, 231
  • [8] Stability Analysis of Surrounding Rock of Water-Rich Tunnel and Optimization of Blasting Construction Method
    Tian, Guobin
    Dai, Jun
    Wu, Yi
    Zhai, Huihui
    JOURNAL OF COASTAL RESEARCH, 2020, : 514 - 517
  • [9] Analysis of deformation control mechanism of prestressed anchor on jointed soft rock in large cross-section tunnel
    Li, Gan
    Hu, Yu
    Tian, Si-ming
    Weibin, Ma
    Huang, Hai-long
    BULLETIN OF ENGINEERING GEOLOGY AND THE ENVIRONMENT, 2021, 80 (12) : 9089 - 9103
  • [10] Analysis of deformation control mechanism of prestressed anchor on jointed soft rock in large cross-section tunnel
    Gan Li
    Yu Hu
    Si-ming Tian
    Ma weibin
    Hai-long Huang
    Bulletin of Engineering Geology and the Environment, 2021, 80 : 9089 - 9103